October 1, 2010 Print
This is the week before Thanksgiving holiday and things are still on schedule and in budget. GREAT WORK EVERYONE!

Still a few more steel beams to install on the ground floor by the front entrance of the new Gallery

While in the back on the ground floor they're trying to finish the installation of the sub floor

The vapour barrier in the second floor bathroom has begun and the insulation is ready to install

The drywall is being measured and cut for the pillar enclosures on the second floor

The "out take" pipes are in for the second floor washrooms

The new "Emergency" stair case has begun ... keep welding it together up, up, up to the fourth floor!

The ground floor windows have been closed with concrete blocks and water sealed